Omexom Ireland Near Completion of The Gorman 110/20kV Substation

Published 19 Jan 2021

Gorman Switchgear Control & Protection Room

Gorman Switchgear Control & Protection Room

  • Article By Paul McCann, Project Manager | Renewables
    
    
    

    Thorne & Derrick secured under competitive tender the order to supply the 33kV Termination & Jointing Materials Package for the medium voltage substation construction from Omexom – this included Size 1- 3 PFISTERER Connex Inner Cone Bushing Connectors and Nexans Euromold Interface C standard and piggy-back configuration Outer Cone Bushing Connectors. Previously, T&D had supplied the Omexom cable jointing teams with cable preparation tools for the safe and efficient stripping of medium voltage cables. 


Gorman 110/20kV High Voltage substation

Omexom Ireland are finishing up work on the new Gorman 110/20kV substation. The substation is located 2km outside of Slane in county Meath, Ireland, with work starting in July 2021 and finalising by the end of January 2022. The €2.4M contract was awarded from Scottish Power Renewables for the complete design and build of the 110/20kV substation to enable the connection of a 50MW battery storage complex.

Omexom Ireland are finishing up work on the new Gorman 110/20kV substation. The substation is located 2km outside of Slane in county Meath, Ireland, with work starting in July 2021 and finalising by the end of January 2022.

The €2.4M contract was awarded from Scottish Power Renewables for the complete design & build of the 110/20kV substation to enable the connection of a 50MW battery storage complex. The project is part of a contestable works model introduced in Ireland recently meaning it had to comply with all the Eirgrid/ESBN construction standards.

The new Gorman substation was designed, constructed & commissioned by Omexom Ireland to the Local TSO operator’s specifications (Eirgrid/ESBN). Construction of the substation included: 110kV sealing ends; Current Transformers (CT) and Voltage Transformers (VT); Surge arrestors; a 60Mva transformer (110kV to 20kV); a complete switchgear control building as well as all the necessary auxiliary systems, complete with control & protection panels to operate and protect the 3 panel NX Plus 20kV switchgear supplying the 50MW battery storage complex including 7kM of 20kV cabling.

Once completed at the end of the month the Gorman 110/20kV substation will provide vital grid stability services to the Northern Dublin area.


Joints Terminations Connectors Lugs


SUPPLYING CABLE TERMINATION, JOINTING, PULL-IN & ELECTRICAL EQUIPMENT UP TO 66KV

Specialist Distributors to the UK and international Offshore Wind & Renewable industry to provide safe and reliable LV HV Electrical Cable & Power Distribution Systems up to 66kV – we are highly customer responsive and absolutely committed to providing a world-class service. Contact our UK Power Team for competitive quotations, fast delivery from stock and technical support or training on all LV-HV products.

Key Product Categories: Duct Seals | Cable Cleats | Cable Glands | Electrical Safety | Arc Flash Protection | Cable Jointing Tools | Cable Pulling | Earthing | Feeder Pillars | Cable Joints LV | Joints & Terminations MV HV 

NOF Offshore Wind Industry