A Photoblog: 138kV Southwire Cable Pull & Termination by Allteck Contractors

Published 15 Dec 2020

This Article was originally published in September 2015.

Andy O’Malley and Jimmy Nicklin have been jointing cables together for more than a decade.

Andy is a 420kV Cable Jointer and EHV Cable installation Allteck - Cable Jointing Supervisor while Jimmy Nicklin is an HV/EHV Cable Jointer, Splicer and acknowledged oil cable expert up to 500kV.

Both are employed by Allteck, international leaders in the design, construction, maintenance and upgrade of overhead and underground high voltage electric power utilities.

The following sequence of site installation photographs demonstrate the high skill levels deployed by the Allteck team in the cable pulling, termination and installation of a Southwire Canada 138kV cable system.

Southwire Company is North America’s leading manufacturer of wire and cable used in the distribution transmission of electricity.

Together, Allteck and Southwire Canada deliver power 24-7-365.

We all take electric power, heat and light for granted. Until we suffer blackout.

Let us offer thanks to those who power our homes and businesses through the simple act of flicking a switch.

To the Splicers and Linemen who face sleepless nights, dizzying heights, atrocious weather and the constant threat of electric shock.

To the pioneering Cable Manufacturers striving to advance technology and improve the reliability of power systems, whether underground or overhead.

Thank you Allteck and Southwire Canada.

Images Courtesy : Andy O’Malley & Jimmy Nicklin

Installation Credit : Andy O’Malley, Jimmy Nicklin & Allteck Crew

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

Jetset Jointers – Head in the clouds but feet firmly on the ground. Flying into Ontario the Allteck Team will be talking through the “game plan” for the 138kV Southwire cable installation. Working at high voltage and high height is high risk. “Great Safety is Great Business” is Allteck’s maxim and No.1 core value.

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

Sub-Zero – Sharp chill in the air and a hard ground frost with the dawn sun reflecting on the frozen ice as the Allteck Team arrive at the job site.

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

Getting Started – cable jacket scraping is key stage of EHV cable preparation.

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck ContractorsA Photoblog: 138kV Southwire Cable Pull & Termination by Allteck Contractors A Photoblog: 138kV Southwire Cable Pull & Termination by Allteck Contractors A Photoblog: 138kV Southwire Cable Pull & Termination by Allteck Contractors

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

Lift-Off – cable pulling commences with completion of the cable chute.

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

Heave-Ho – cables pulled up monopole ready for scaffolding and then terminating.

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

Tools of the Trade – cable jointers must hold the correct cable jointing tools to strip and remove cable jacket, cable insulation and cable semi-conductive screens from high voltage cables.

Cable Jointing - high voltage cable stalk positioned and sealed.

Cable Jointing – high voltage cable stalk positioned and sealed.

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

If The Cap Fits - hard hat swapped out for baseball cap worn for critical parts of the job once the cable oversheath has been removed as it is critical to not damage the cable insulation.

If The Cap Fits – hard hat swapped out for baseball cap worn for critical parts of the job once the cable oversheath has been removed as it is critical to not damage the cable insulation.

Wiping Down - a highly skilled stage of cable termination

Wiping Down – a highly skilled stage of cable termination

A Master Craftsman - Jimmy Nicklin (Allteck) showing the world how to "wipe".

A Master Craftsman – Jimmy Nicklin (Allteck) showing the world how to “wipe”.

Stripping Off - removal of semi-con screen using Hivotec CP90 jointers tool.

Stripping Off – removal of semi-con screen using Hivotec CP90 jointers tool.

No Cheating On Cleating - installing transmission cable cleats to retain the 138kV cable in the event of short-circuit condition (as if). Southwire cable supported by Southwire cable cleats installed by Allteck crew.

No Cheating On Cleating – installing transmission cable cleats to retain the 138kV cable in the event of short-circuit condition (as if). Southwire cable supported by Southwire cable cleats installed by Allteck crew.

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors

Mission Accomplished - completed NKT ODSE 138kV Cable Termination

Mission Accomplished – completed NKT ODSE 138kV Cable Termination

A Photoblog : 138kV Southwire Cable Pull & Termination by Allteck Contractors


Why Specify Southwire?

138kV Southwire Cable Specification & Benefits

  • Compressed Round or Compacted Segmental Conductor
  • Corrugated Metallic Sheath or Copper Laminate Sheath
  • True Triple Extrusion
  • Super Clean XLPE Cable Insulation
  • Insulation Thickness 650 mils-850 mils

Southwire 138kV Power Cable

Conductor Material & Size

The choice of the conductor material, copper or aluminium, is a matter of customer preference and required current carrying capacity. For larger loads, copper is the most common option. When both copper and aluminium conductors can satisfy power system requirements, the more economical solution will be a function of the metal and the cable components costs in effect.

Insulation Thickness
Cables referred to by “Traditional Wall” insulation (850 mils) follow the traditional insulation wall practice referenced in ICEA standard S-108-720 appendix F as still specified by a number of customers and utilities. For cables with a radial moisture barrier, “Southwire(SW) Standard Wall” thicknesses of 650 mils in accordance with AEIC specification CS9 are recommended. For applications requiring smaller cable diameters, cables with reduced insulation thickness are available upon request within the stress limits in AEIC specification CS9.

Cable Sheath Material
Copper and aluminium corrugated sheaths offer the best mechanical and moisture protection for HV cable. In addition, copper will provide better short circuit performance and improved connectability. Another option is Southwire composite laminate sheaths in both copper and aluminium that offer excellent protection against moisture ingress.

Cable Jacket
Southwire standard outer jacket is extruded LLDPE with a co-extruded outer semi conductive polyethylene layer for jacket integrity testing. Halogen Free Fire Retardant (HFFR) compounds are available upon request for installations in cable trays and ventilated troughs.

Southwire

Southwire is one of the world’s leading manufacturers of Wire and Cable, Tools, Components and Assembled Solutions.

“We Want To Produce The Best Wire Products”

Southwire is one of the world’s leading developers, manufacturers and suppliers of building wire and utility cable, as well as the cable tools used in their installation. As such, Southwire are continually improving their products, studying how they’re used in the field and assessing the needs of their customers to find new and better ways to solve the problems facing the industry.

Allteck Line Contractors and Quanta Energized Services


Jointers blog

Subscribe now to our POWER NEWSLETTER– a monthly email circulation packed with news, projects, videos, technical tips, training information, promotions, webinars, career opportunities and white papers.

Includes access to our popular JOINTERS BLOG with contributions from utility professionals, linesmen and cable jointers working on MV HV EHV cables and overhead lines typically at 11kV, 33kV, 66kV and up to 132kV.

15,000+ Subscribers. âž¡ Joints Terminations Cleats Lugs MV HV 11kV 33kV