3-Phase 16sqmm to 35sqmm Plastic CNE Cable Joint

3-Phase 16sqmm to 35sqmm Plastic CNE Cable Joint

3-Phase 16sqmm to 35sqmm Plastic CNE Cable Joint

Cable Joint Installation Instructions

Sicame SSJ5/UPN

For details of cable preparation, the installation of mechanical connectors and associated components refer to the relevant sections of the UK Power Networks LV Jointing Manual opposite.

All dimensions in millimetres (mm).

  • Overlap the ‘live’ service cable with at least 300mm of the new cable
  • Set the cables into their final jointing position and strip the cables using the plastic joint shell as a guide
  • Position a temporary core shroud over the ‘live’ cable core
  • Fit the MFB4/28i connector onto the neutral earth wires
  • Fit the MFB4/28i connector onto the phase cores, one at a time
  • Fit the cable joint shell, checking for a minimum clearance of 10mm between the joint shell and the completed cable joint
  • Fill the cable joint shell with the correct amount of Prysmian JEM resin as shown in the table below

Cable Jointing Materials

Cable Size (sqmm) UKPN Stores Code Sicame Cable Joint Kit Number Empty Shell Jointing Resin Volume
16sqmm 16sqmm 02710V SSJ5/UPN 3.4 Litres
35sqmm 35sqmm
3-Phase 16sqmm to 35sqmm Plastic CNE Cable Joint

Sicame SSJ5/UPN Cable Joint

♦ Note: LV Cable Joints are subject to change according to tender contract awards, manufacturer joint kit amends and new cable applications – always check with Thorne & Derrick that the kit referenced is the current approved and available cable joint.