Head Office
C&P Engineering Services Ltd
Gorseinon Road
Gorseinon
Swansea
SA4 9GE
Phone: +44 (0)1792 897002
Fax: +44 (0)1792 895193
Email: [email protected]

uploaded by Chris Dodds - reading time 2 minutes
The following Cable Jointing Tools are approved and used by Jointers working for or on behalf of Scottish Power Energy Networks (SPEN) for the preparation of 11kV/33kV power cables prior to the installation of MV HV Joints, Terminations & Connectors.
| Cable Jointing Application | Tool Type | Comments | Manufacturer |
| MDPE Cable Sheath Stripper | KMS-S | na | |
| Cable Stripping Pliers | Alroc PG3 | Width 2.8mm cutting wheels, for cable diameter 30-55mm PICAS | Alroc |
| Cable Stripping Pliers | Alroc PG4 | Width 3.0mm cutting wheels, for cable diameter 45-75mm PICAS | Alroc |
| XLPE Screen Stripping Tool (Easy strip/Peelable) | Alroc LHM1R | Adjustable screen scoring tool 14-40mm diameter cables | Alroc |
| XLPE Screen Scoring Tool | Prysmian TT2352/1 | 0.4mm (for use on 33kV cables) | Prysmian |
| XLPE Screen Scoring Tool | Prysmian TT2352/2 | 0.6mm (for use on 11kV cables) | Prysmian |
| XLPE Screen Stripping Tool (Fully Bonded Screen) | INT.BZ Mod. 1714 | 10-52mm | Boddingtons |
| XLPE Screen Stripping Tool (Fully Bonded Screen) | NKT 500 30 | 16-40mm | NKT |
| XLPE Screen Stripping Tool (Fully Bonded Screen) | Alroc ASC40R2 | 38-60mm diameter cables (630sqmm cables) | Alroc |
| XLPE Adjustable XLPE Insulation Stripping Tool | Alroc BRMrd1 | 14-40mm | Alroc |
| XLPE Adjustable XLPE Insulation Stripping Tool | Alroc BRMrd2 | 38-60mm | Alroc |

Alroc Tools | Remove Sheath | Remove Screen | Remove Insulation
♦ See also: Scottish Power Energy Networks Approved | Cable Joints, Terminations & Electrical Equipment LV HV
➡ Visit Alroc to view the complete range of Jointers Tools for stripping and preparing 11kV/33kV power cables – cable tools also available for 66kV-132kV cable jointing and preparation.

Insulation | Screen | Sheath | Cable Preparation Tools 11kV 33kV
JOINT ♦ TERMINATE ♦ CONNECT ♦ GLAND ♦ CLEAT ♦ CRIMP ♦ DUCT ♦ SEAL ♦ REPAIR ♦ CABLE ♦ SPLICE ♦ INSULATE

The 66kV 3 core high pressure (200 psi) gas joint (nitrogen) was made for SSE by Matthew Taffs of CRS Ltd and John Beck both working for Balfour Beatty at the time.
The 66kV cable construction was oval copper conductor with a lead sheath and steel reinforcing tapes with hessian wrapped layer. The manufacturer of the cable joint was Glovers (W T Glover) of Trafford Park, Manchester which later became part of BICC.
The cable joint is from the 1950’s and when the joint was unpacked from the wooden create it was still packed in straw. The insulation of the cable had to be stepped down to the conductor known as pencilling using piano wire and weights.
The joint consisted of a two piece split ferrules which was sweated on the conductor with tinmans metal. Once sweated the ferrule was cleaned up and the insulation was ready to be applied. The insulation was flat/plain paper tapes (not crepe) coated in a thin layer of grease and was applied with care by the jointer. Once built up to the final diameter the end profiles had to be skilfully teared down using piano wire and weights again. The metallic screen reinstated from one side to the other and then each core is covered in terylene tape.
Both end cable glands of the joint had internal plumbs /wipes and when the plumbing was finished – hot oil was poured on followed by a hot metal into the cable gland to reinforce the steel tapes and lead sheath as this 66kV cabling system is such high pressure it would split the lead sheath.
Once the 66kV joint was finished the jointer bolted the sleeve to the cable gland and turn on the nitrogen gas and check for leaks. The 66kV joint could be protected in either a Glo (Glovers) Sleeve filled with compound/ bitumen or heat shrink. The job was project managed by Gary Horne, now of CRS (Cable Repair Services) Ltd.

66kV 3 Core Glovers Gas (HP) Cable Joint
21st century cable manufacturing is dominated by polymeric type insulated cables and for offshore wind farm power generation including subsea power, array, inter-array and intra-array cables – to support this type of 66kV high voltage cable infrastructure Thorne & Derrick via their distribution agreement with Nexans can supply a complete range of joints, terminations, connectors and surge arresters detailed below.

Ad: Two Times More Power. Jointers! Empower your CV and skill-set by grasping the 66kV Jointer Training opportunity. Jointers must currently be 33kV Competent and experienced to be ready to undertake the step-up to 66kV from 33kV.
Pictured: Prysmian type tested a 3-core 66kV EPR insulated “wet-design” cable system with aluminium conductor (copper is also available) – and integrated optical element. The solution includes factory, field cable joints, plug-in cable terminations and cable cleats, using proprietary Prysmian Click-Fit™ technology combinings the use of EPR insulation.

66kV Cables – Offshore Wind Farms
Walter T. Glover & Co of Trafford Park, Manchester and London, were electrical cable manufacturers.
1868 – Company founded with premises at the Bridgewater Street Iron Works in Salford. The founder, Walter T. Glover, was a commercial machinery agent for the Lancashire cotton industry.
1959 – BICC acquired 50% of Submarine Cables Ltd which was used to manufacture and install power cables. Glover’s submarine cables were used to link England and France, and the north and south islands of New Zealand. However, although the company appeared to be doing well, there was increasing international competition to supply cables. The south side of the Trafford Parks works was integrated into the newly formed Wiring and General Cables Division of British Insulated Cables (BICC).
Trip down memory lane…………….

W.T. Glover, Trafford Park, cable being laid over a cofferdam, 1911

W.T. Glover, Trafford Park, Installation of cabling in Ebbw Vale, 1905

W.T. Glover, Trafford Park, installation of cabling, with motor vehicle clearly visible, 1905

W. T. Glover and Co – 1970 The Trafford Park factory was closed, but the Glover brand continued as part of BICC.

LV ♦ MV ♦ HV
T&D distribute the most extensive range of LV, MV & HV Cable Jointing, Terminating, Installation & Cable Pulling Equipment – we service UK and international clients working on underground cables, overhead lines, substations and electrical construction at LV, 11kV, 33kV and EHV transmission and distribution voltages.

LV – Low Voltage Cable Joints, Glands, Cleats, Lugs & Accessories (1000 Volts)

MV HV – Medium & High Voltage Cable Joints, Terminations & Connectors (11kV 33kV EHV)

Cable Laying – Underground Cable Covers, Ducting, Seals & Cable Pulling Equipment
T&D’s Power Blog covers: LV MV HV & EHV Transmission & Distribution, Substations, Switchgear, Cable Jointing & Termination, Cable Fault & Repair, Underground Cables
➡ Visit Power Blog


C&P Awarded Contract for 30MW STOR Gas Generation Facility
Press Release By Tristan Jones (Sales & Marketing Manager - C&P Engineering Services Ltd)
C&P Engineering Services are delighted to announce that is has been awarded the design and build contract by Enersyst Limited (part of the Walters Group of Companies) for a STOR (Short Term Operating Reserve) 30MW Gas Generation Facility, located off Smoke Lane in Avonmouth, Bristol.

The 30MW STOR facility is one of a number of projects created to service National Grid balancing services. STOR is a demand-side service used by National Grid to provide additional active power from generation or demand reduction. The contract will include full civil and electrical design and build balance of plant works and will include designing, engineering, supplying, installing, constructing, testing and commissioning a fully furnished and operational 30MW gas STOR generation facility.
The project will finally consist of fifteen containerised gas powered gensets, together with associated infrastructure, including vehicle access, pedestrian walkways, foundations, site electrical works, SCADA, substation, control room, transformer and other ancillary items.
The site was first developed in the mid-1960s by Butler Chemicals and was subsequently occupied by Albright and Wilson (1967), Tennaco (1984) and Rhodia (2000). Albermarle Chemicals UK Ltd purchased the site from Rhodia in 2003. The majority of the demolition completed by early 2013.
Over the next 12 months C&P will be working on the design, electrical infrastructure, scada system, cable system, switchgear, M&E fit out of the control building, auxiliary supply to the control building, grid compliance, design of capacitor bank, design and installation of earthing network, testing, commissioning and energisation of the 33kV private network.
David Demock, HV Engineering Manager commented: “This is C&P’s first project with Enersyst and we’re excited to deliver the full balance of plant elements of this 30MW site and a fully operational gas STOR generation facility”.
C&P Engineering Services deliver specialist High Voltage Electrical Services to a diverse range of customers in the oil, gas, chemical, petrochemical, heavy engineering, industrial, commercial, construction, renewable energy and nuclear sectors. Services cover design, erection, testing and commissioning and operating for both new HV electrical installation and refurbishment up to and including 132kV.
C&P Engineering Services is an electrical and instrumentation engineering solutions provider, providing specialised HV Design & Build Services for 11kV, 33kV and up to 132kV electrical distribution networks. C&P’s high voltage division delivers full balance of plant works for high voltage electrical projects such as STOR, Battery Storage, Wind Energy, Bio Mass, Marine, Offshore Wind, Manufacturing, Nuclear, Petrochemical, Oil and Gas, Chemical and Power Generation.
C&P’s other integrated EC&I engineering services can be combined to provide the total EC&I engineering solution or divided into the following design & build and operation and maintenance specialist areas:
• Instrumentation, Control & Automation
• High Voltage & Extra High Voltage – 11kV | 33kV | 132kV
• Low Voltage Electrical
• Hazardous Area ATEX Electrical & Instrumentation

Head Office
C&P Engineering Services Ltd
Gorseinon Road
Gorseinon
Swansea
SA4 9GE
Phone: +44 (0)1792 897002
Fax: +44 (0)1792 895193
Email: [email protected]
THORNE & DERRICK are national distributors of LV, MV & HV Cable Installation, Jointing, Duct Sealing, Earthing & Electrical Equipment – we service UK and global businesses involved in cable installations, cable jointing, substation, overhead line and electrical construction at LV, 11kV, 33kV and EHV.
Contact us for 3M Electrical, ABB, Alroc, AN Wallis, CATU Electrical, Cembre, Centriforce, CMP, CSD, Elastimold, Ellis Patents, Emtelle, Euromold, Filoform , Furse, Lucy Electric & Zodion, Nexans, Pfisterer, Polypipe, Prysmian, Roxtec, Sicame, WT Henley.
Thorne & Derrick invite you to join LinkedIn’s largest LV-HV Electrical Discussion Group : Low & High Voltage Power, Cabling, Jointing & Electricals.
Discussion subjects include cable installations, cable jointing, substation earthing, overhead line and electrical construction at LV, 11kV, 33kV and EHV.
Network, engage and promote your profile, company or products with over 10,000 influencers.

![]()
BICON cable cleats form part of the LV-HV cable accessory product range manufactured by Prysmian – this also includes cable glands, cable lugs, cable joints and cable terminations.
T&D distribute the complete range of BICON cable cleats and clamps including plastic nylon (LSF), aluminium and stainless steel Multicleats for supporting LV, MV, HV cables installed on all types of cable containment including basket, ladder or tray in plant rooms, electricity substations and electrical building services infrastructure.
Cable cleats are used to protect electrical building services, power supply and infrastructure by providing effective short circuit restraint in fault current situations – cleats are available for single, double and multiple cable applications.
Where single core cables must be clamped in a three phase arrangement trefoil cable cleats can be used to provide effective short circuit protection.
British Insulated Callender’s Cables (BICC) was a 20th-century British cable manufacturer formed in 1945 by a merger of Callender’s Cable & Construction Company Limited and British Insulated Cables – in 1975 the company was renamed BICC Ltd.
The BICON brand originates from BICC Components.
The BICON product range is the result of 100+ years of LV-HV cable accessory development and quality engineering started by BICC and continued in the 21st Century by Prysmian Cables and Systems Ltd, UK.
The full range of BICON brand cable accessories include Prysmian cable cleats, glands, joints and connectors for sectors including utilities, construction, rail, infrastructure and oil and gas industries. These are marketed under the BICON brand, manufactured by Prysmian and distributed by Thorne & Derrick.
![]()

Cable cleats are installed to provide short circuit protection to electric cables distributing power at low, medium and high voltage – a complete range of cable cleats are available to support the installation of power, control and instrumentation cables in single, trefoil, quad or bundled arrangement to cable containment in commercial, industrial and hazardous area locations including 11kV/33kV substations.
Single Way Cleats | Trefoil Cleats | Fire Resistant Cleats plus a complete range of aluminium cable cleats ➡ 2 Bolt | Hook | Claw
View the complete range of BICON Cable Cleats ➡

by Chris Dodds T&D - estimated reading time 5 minutes







T&D distribute the most extensive range of MV & HV Cable Joints & Terminations, Cable Installation Accessories & Cable Pulling Equipment – we service UK and international clients working on underground cables, overhead lines, substation earthing and electrical construction at LV, 11kV, 33kV and EHV transmission and distribution voltages.

LV – Low Voltage Cable Joints, Glands, Cleats, Lugs & Accessories (1000 Volts)

MV HV – Medium & High Voltage Cable Joints, Terminations & Connectors (11kV 33kV EHV)

Cable Laying – Underground Cable Covers, Ducting, Seals & Cable Pulling Equipment
T&D’s Power Blog covers: LV MV HV & EHV Transmission & Distribution, Substations, Switchgear, Cable Jointing & Termination, Cable Fault & Repair, Underground Cables.
➡ Visit Power Blog.
