The Successful Trial of the New Overhead Line Equipment (OLE)
Network Rail Training colleagues shine a spotlight on electrical safety after successfully trialling new overhead line equipment (OLE). The alternative socket and adapter combination was tested by workforce development specialists at Walsall training centre looking to improve safety for colleagues carrying out overhead line maintenance and, by extension, passengers and freight users.
A successful trial
Following an incident at the centre during an Authorised Person training course where a delegate was struck by a falling clamp that had come loose in its socket, the supplier, PBwel, was contacted and challenged to provide an engineering solution to reduce the risk of repeat incidents.
Gavin Brandrick, Workforce Development Specialist (Team Leader), listened to the supplier’s advice and immediately set up a trial of a different socket and adapter more suited to the task of attaching specific earthing wires (Long Blue Earths) to overhead lines.

Interlocked Long Blue Earth: specially enhanced to address the potentially fatal procedure of removing the equipment in the incorrect order of use
The trial was conducted by a team of workforce development specialists and OLE Authorised Persons, under guidance from PBwel and a representative from Safety, Technical and Engineering (STE), all of whom deemed it a success.
Gavin Brandrick said, “All feedback was positive with the staff saying they felt more confident that the earth would not fall due to the improved design of the socket. All staff applied and removed the earth without any problems after a quick brief and demonstration”.
The alternative equipment is now being further trialled by STE and, if successful, will be considered for national rollout – a prime example of how the safety of the training environment can be used to develop solutions and new ways of working for the live railway.
Professional curiosity and a passionate commitment
John Partington, SHE specialist and accident investigator, said: “The response to the accident, investigation and prospective solution has revealed a safety culture among the training team at Walsall training centre which is a credit to them and an asset to Network Rail.
“When faced with the challenge of an alternative way of working, the workforce development specialists did not offer barriers to change based on their years of using the existing kit; they showed professional curiosity and a passionate commitment to Network Rail’s drive for ‘better every day’ by not only accepting the possibility of change, but by running with the idea and owning the initiative. This is the type of safety culture to be celebrated in Network Rail.
To our workforce development specialists Robert Brandrick and Steven Urie, who conducted the trial – thank you. There is a real possibility of Network Rail seeing a significant safety improvement due to your attitude – and that is clearly an example of ‘Putting Passengers First’!”

PB WEIR – DISTRIBUTORS, STOCKISTS & SUPPLIERS
PB Weir Substation Earthing and Transmission Line Earthing Equipment include line end clamps, earth end clamps, portable earthing leads and operating poles for high voltage substations, overhead power line and transmission line applications – voltages include 11kV, 33kV, 66kV, 132kV up to 400kV.
Thorne & Derrick provide competitive prices and fast delivery from stock for the complete range of PB Weir substation earthing and transmission line earthing equipment.
In 2018 In 2018 PB Weir joined the Novarc group and re-branded as PBwel and now, through the ESP group of companies, we are able to supply, support and maintain a comprehensive range of Electrical Safety Equipment which includes: Earthing, Insulated Tools, Arc Flash Protection, Personal Voltage Detection Helmets, Insulating Gloves, Voltage Detection, Operating Poles & Lock-Out Tag-out.

ALADIN | Improved electrical safety levels for workers operating near live equipment
➡ Read More Here: ALADIN Individual Voltage Alarm With Headlamp For MV Overhead Lines 10-69kV

Product Spotlight | see Live Line Indicators designed for use upon overhead a.c. rail electrification systems operating at 25kV nominal voltage to indicate the presence of extra high voltages to aid safe working practices.
Further Reading
- E-Shark Safety Helmet By PBwel
- MTAG DR 69 kV Multi Voltage Detector Dual Range
- Substation Suspended Earthing Spigots By PBwel
- Drain Earths | PBwel 50sqmm Arctic Orange Field Drain Earth
- PBwel Transmission Line Earthing Leads 132kV, 275kV, 400kV
- Long Blues | Rail Portable Earthing By PBwel | Network Rail Approved
- PBwel Earthing Leads For Temporary Earthing Of Transmission Line Conductors 132kV, 275kV, 400kV
LV, MV & HV JOINTING, EARTHING, SUBSTATION & ELECTRICAL EQPT
Thorne & Derrick International are specialist distributors of LV, MV & HV Cable Installation, Jointing, Duct Sealing, Substation & Electrical Equipment – servicing UK and global businesses involved in cable installations, cable jointing, substation, overhead line and electrical construction at LV, 11kV, 33kV and EHV.

Omexom Ireland Near Completion of The Gorman 110/20kV Substation
January 19th, 2021
Gorman Switchgear Control & Protection Room
-
Article By Paul McCann, Project Manager | Renewables
Thorne & Derrick secured under competitive tender the order to supply the 33kV Termination & Jointing Materials Package for the medium voltage substation construction from Omexom – this included Size 1- 3 PFISTERER Connex Inner Cone Bushing Connectors and Nexans Euromold Interface C standard and piggy-back configuration Outer Cone Bushing Connectors. Previously, T&D had supplied the Omexom cable jointing teams with cable preparation tools for the safe and efficient stripping of medium voltage cables.
Gorman 110/20kV High Voltage substation
Omexom Ireland are finishing up work on the new Gorman 110/20kV substation. The substation is located 2km outside of Slane in county Meath, Ireland, with work starting in July 2021 and finalising by the end of January 2022. The €2.4M contract was awarded from Scottish Power Renewables for the complete design and build of the 110/20kV substation to enable the connection of a 50MW battery storage complex.
Omexom Ireland are finishing up work on the new Gorman 110/20kV substation. The substation is located 2km outside of Slane in county Meath, Ireland, with work starting in July 2021 and finalising by the end of January 2022.
The €2.4M contract was awarded from Scottish Power Renewables for the complete design & build of the 110/20kV substation to enable the connection of a 50MW battery storage complex. The project is part of a contestable works model introduced in Ireland recently meaning it had to comply with all the Eirgrid/ESBN construction standards.
The new Gorman substation was designed, constructed & commissioned by Omexom Ireland to the Local TSO operator’s specifications (Eirgrid/ESBN). Construction of the substation included: 110kV sealing ends; Current Transformers (CT) and Voltage Transformers (VT); Surge arrestors; a 60Mva transformer (110kV to 20kV); a complete switchgear control building as well as all the necessary auxiliary systems, complete with control & protection panels to operate and protect the 3 panel NX Plus 20kV switchgear supplying the 50MW battery storage complex including 7kM of 20kV cabling.
Once completed at the end of the month the Gorman 110/20kV substation will provide vital grid stability services to the Northern Dublin area.
SUPPLYING CABLE TERMINATION, JOINTING, PULL-IN & ELECTRICAL EQUIPMENT UP TO 66KV
Specialist Distributors to the UK and international Offshore Wind & Renewable industry to provide safe and reliable LV HV Electrical Cable & Power Distribution Systems up to 66kV – we are highly customer responsive and absolutely committed to providing a world-class service. Contact our UK Power Team for competitive quotations, fast delivery from stock and technical support or training on all LV-HV products.
Key Product Categories: Duct Seals | Cable Cleats | Cable Glands | Electrical Safety | Arc Flash Protection | Cable Jointing Tools | Cable Pulling | Earthing | Feeder Pillars | Cable Joints LV | Joints & Terminations MV HV

Earthing Spigots | Substation Suspended Earthing Spigots By PBwel
January 12th, 2021
Substation Spigots
Substation Suspended Earthing Spigots
The PBwel Substation portable earthing equipment range is designed to meet the specific requirements of ENA Technical Specification 41-21.
PBwel offer range of spigots such as Suspended Busbar Spigot, Type A & Type B Aluminium Spigots, Type C Spigot, Type D Spigot and Type H Suspended Busbar Aluminium Spigot.
All PBwel Spigots are designed to be permanently fitted to a new or existing busbar. The PBwel spigots have a proven track record of assurance and quality, which has been fully approved and tested by the National Grid and are in use throughout the UK substations.
Suspended Earthing Spigot
Performance Characteristic
- 1kN Mechanical Load
- 900 Amps Continuous Current Rating
- RIV and Corona Discharge Test @ 400kV Rating
- 80kA/1s Short Circuit Rating including a peak at 200kA
- 40kA/3s Short Circuit Rating including a peak at 100kA
Suspended Busbar types and part numbers
| Product Preference | Body Part Number | Spigot Part Number | Busbar Size (mm) |
| CE75/250 | EFF-16771 | EFF-16780 | 250 |
| CE75/220 | EFF-16772 | EFF-16780 | 220 |
| CE76/200 | EFF-16773 | EFF-16780 | 200 |
| CE76/190 | EFF-16774 | EFF-16780 | 190 |
| CE76/160 | EFF-16775 | EFF-16780 | 160 |
| CE77/140 | EFF-16776 | EFF-16780 | 140 |
| CE77/127 | EFF-16777 | EFF-16780 | 127 |
| CE77/120 | EFF-16778 | EFF-16780 | 120 |
| CE77/115 | EFF-16779 | EFF-16780 | 115 |
* Note: A Suspended Busbar requires both a body and spigot assembly as shown upon the chart.
Suspended Earthing Spigot Range
- Quick Installations
- Can be set up by one person
- Suitable for existing and new busbars
- National Grid Approved
Substation Spigot Range
![]() |
![]() |
![]() |
![]() |
| Bolt On Corona Shields For Spigots | Suspended Busbar Spigot CE75, CE76 & CE77 | Type A Aluminium Spigots | Type B Aluminium Spigots |
![]() |
![]() |
![]() |
![]() |
| Type C Spigots | Type D Spigots 63.5 230 Aluminium | Type E Spigots | Type H Spigots Suspended Aluminium Spigot |

PB WEIR – DISTRIBUTORS, STOCKISTS & SUPPLIERS
PB Weir Substation Earthing and Transmission Line Earthing Equipment include line end clamps, earth end clamps, portable earthing leads and operating poles for high voltage substations, overhead power line and transmission line applications – voltages include 11kV, 33kV, 66kV, 132kV up to 400kV.
Thorne & Derrick provide competitive prices and fast delivery from stock for the complete range of PB Weir substation earthing and transmission line earthing equipment.
In 2018 In 2018 PB Weir joined the Novarc group and re-branded as PBwel and now, through the ESP group of companies, we are able to supply, support and maintain a comprehensive range of Electrical Safety Equipment which includes: Earthing, Insulated Tools, Arc Flash Protection, Personal Voltage Detection Helmets, Insulating Gloves, Voltage Detection, Operating Poles & Lock-Out Tag-out.

ALADIN | Improved electrical safety levels for workers operating near live equipment
➡ Read More Here: ALADIN Individual Voltage Alarm With Headlamp For MV Overhead Lines 10-69kV

Product Spotlight | see Live Line Indicators designed for use upon overhead a.c. rail electrification systems operating at 25kV nominal voltage to indicate the presence of extra high voltages to aid safe working practices.
Further Reading
- E-Shark Safety Helmet By PBwel
- MTAG DR 69 kV Multi Voltage Detector Dual Range
- Network Rail Case Study New Overhead Line Equipment
- Drain Earths | PBwel 50sqmm Arctic Orange Field Drain Earth
- PBwel Transmission Line Earthing Leads 132kV, 275kV, 400kV
- Long Blues | Rail Portable Earthing By PBwel | Network Rail Approved
- PBwel Earthing Leads For Temporary Earthing Of Transmission Line Conductors 132kV, 275kV, 400kV
LV, MV & HV JOINTING, EARTHING, SUBSTATION & ELECTRICAL EQPT
Thorne & Derrick International are specialist distributors of LV, MV & HV Cable Installation, Jointing, Duct Sealing, Substation & Electrical Equipment – servicing UK and global businesses involved in cable installations, cable jointing, substation, overhead line and electrical construction at LV, 11kV, 33kV and EHV.

Alroc BRMRD1- XLPE Insulation Removal & Stripping Tool | Video
January 12th, 2021
Alroc BRMRD1 MV HV Cable Jointing Tool
Insulation Removal & Stripping Tool
By Alroc
MV HV Medium & High Voltage Cables
The below video shows the Alroc BRMRD1 insulation removal stripping tool in use by cable jointers removing the XLPE insulation to prepare the cable ready for the installation of cable joints, terminations or connectors.
Cable preparation is essential to the performance and stability of MV-HV cable joints and terminations – if cables are prepared incorrectly using sub-standard tools or basic hand tools then the risk incidence of cable failure is increased.
The BRMRD1 cable tools manufactured by Alroc enable the cable jointer to set the length and remove the XLPE insulation with a straight and neat cut on MV cables and are predominantly used by MV-HV cable jointers.
The following instructions detail how to use the BRMRD1 insulation removal and stripping tool safely and effectively.
- Firstly set up the handle on the cable jointing tool
- Then set up of the thrust of the BRMRD1 tool
- Tighten the tool on the MV HV cable
- Ensure to check the blade setting by making a full turn
- Then securely lock the blade in position
- Once locked in position set the length of the insulation to be removed
- Remove the insulation until the thrust touches the conductor
- Once complete unlock the blade and screw it back before loosening and withdrawing the insulation removal stripping tool
Alroc BRMRD1E – Technical Specification
| Cable Tool Part Number | Diameter | Tool Capacity | Dimensions | Packaging | ||
| Insulation Thickness Capacity | Length | Width | Height | |||
| BRMRD1E | 14 – 40 mm / 0.551 – 1.575 in | 9 mm / 0.354 in | 270 mm / 10.630 in | 100 mm / 3.937 in | 165 mm / 6,496 in | None |

Alroc Cable Tools 11kV 33kV MV HV
ALROC
For more than 30 years, ALROC has been engineering, designing and manufacturing cable jointing tools, cable preparation tools and cable fixing solutions to establish the most complete product range in the following areas:
- LV cable
- MV cable
- HV cable
- Optical Fibre cable and tube
- Telecomunications cable
- Coaxial cable
- Steel gas pipe
- Cable holding and fixing solutions

Jointing & Preparation Tools For Cable Jointers & Linesmen Working On MV-HV-EHV Cables
THORNE & DERRICK
Thorne & Derrick are national distributors of LV, MV & HV Cable Installation, Jointing, Substation & Electrical Equipment – servicing businesses involved in cabling, jointing, substation, earthing, overhead line and electrical construction at LV, 11kV, 33kV, 66kV and EHV. Supplying a complete range of power cable accessories to support the installation and maintenance of low/medium and high voltage power systems:
- Slip-on Cable Terminations
- Cold-shrink Cable Terminations
- Heat-shrink Cable Terminations
- Cable Joints – Heat & Cold-shrink
- Separable Connectors (Euromold)
- Surge Arresters & Switchgear/Transformer Bushings
Key Product Categories: Duct Seals | Cable Cleats | Cable Glands | Electrical Safety | Arc Flash Protection | Cable Jointing Tools | Cable Pulling | Earthing | Feeder Pillars | Cable Joints LV | Joints & Terminations MV
Arc Flash PPE Safety | Guidance On Protecting UK Rail Contractors
January 12th, 2021Arc Flash PPE Safety – Protecting UK Rail and Utility Contractors
STEP UP FOR SAFETY – Are we doing enough to protect civil engineering and utility contractors working within the railway boundary?

Guest Article: Republished with the kind permission of Integrum Power Engineering.
Arc flash PPE can help protect railway, civil engineering and utility contractors from severe electrical burns. However, protective clothing is only one part of managing electrical hazards.
Workers involved in excavation, power distribution and railway infrastructure may encounter live electrical equipment or buried cables. Without suitable precautions, accidental contact can result in electric shock, arc flash and serious injury.
Following an incident at Network Rail’s Godinton Substation in December 2018, Integrum Power Engineering raised an important question: are existing precautions sufficient for everyone working within the railway boundary?
This article examines the original discussion, electrical safety legislation, workplace incidents and practical steps for improving arc flash risk management.
About Integrum Power Engineering
Integrum Power Engineering provides power distribution engineering services across sectors including rail, utilities, renewables, oil and gas, and private electrical networks.
The company’s services include network modelling, fault analysis, protection system design and substation engineering.
Its original article highlighted the importance of protecting workers through appropriate engineering controls, risk assessment and safe working practices.
What Is an Arc Flash?
An arc flash is a dangerous electrical event involving the release of energy from an electrical arc.
Electrical arcing can generate intense heat and ultraviolet radiation. Depending on the circumstances, it may also produce pressure waves, molten metal and flying debris.
Workers exposed to these effects can suffer serious burns, eye injuries and other life-changing injuries.

What Causes an Arc Flash?
An electrical arc can occur when insulation fails or an unintended conductive path develops between energised components.
Potential causes include equipment defects, contamination, accidental contact and damage to electrical cables.
For example, a powered excavation tool striking a live underground cable may create an electrical fault and expose the operator to serious injury.
The original Integrum article described arc temperatures ranging from 5,000°C to 20,000°C. These figures illustrate the extreme temperatures that electrical arcs can reach, although the actual conditions vary between incidents.
Arc Flash Hazards
Depending on the electrical system and incident, an arc flash may produce:
- Severe thermal burns.
- Intense light and ultraviolet radiation.
- Molten metal and hot particles.
- Pressure waves and flying debris.
- Damage to electrical equipment.
- Fire and secondary injuries.
For this reason, workers need suitable electrical safety procedures before undertaking tasks that could expose them to an arc flash hazard.
Arc Flash Incidents and Workplace Safety Statistics
The original Integrum Power Engineering article highlighted concerns about electrical incidents in the UK.
It referenced figures of approximately 60,000 underground cable strikes annually, alongside around 1,000 workplace electrical incidents reported to the HSE each year.
The article also cited approximately 25 fatalities per year associated with electrical incidents.
However, these are historical figures from the original publication. They have not been independently verified as current annual statistics.

Research into Arc Flash Awareness
The article also referenced research by ProGARM.
According to the original research, 57% of surveyed electrical workers had either experienced an arc flash incident or witnessed someone else being affected.
Although this finding raised concerns about electrical safety awareness, it represents the cited survey rather than a verified incident rate across the entire workforce.
Why Accurate Incident Reporting Matters
Reliable incident data helps organisations understand electrical hazards and improve their prevention measures.
However, statistics covering electrical injuries do not necessarily distinguish arc flash incidents from electric shocks or other electrical accidents.
Therefore, employers should use relevant incident information alongside task-specific risk assessments and workplace investigations.

Historical arc flash injury illustration from the original article – USA.
UK Arc Flash Legislation and Employer Responsibilities
UK health and safety legislation requires employers to assess and manage risks arising from electrical work.
This includes the potential for injury caused by electrical arcing, burns, shock and explosions.
Electricity at Work Regulations 1989
Regulation 4(1) of the Electricity at Work Regulations 1989 states:
“All systems shall at all times be of such construction as to prevent, so far as is reasonably practicable, danger.”
The regulations also address injuries associated with electrical shock, burns, explosions and arcing.
Consequently, employers and duty holders must consider these hazards when planning electrical work.
Management of Health and Safety at Work Regulations 1999
Regulation 3 requires employers to undertake suitable and sufficient assessments of relevant workplace risks.
These assessments must consider employees and other people who may be affected by the employer’s activities.
For example, electrical contractors working near underground cables may face hazards that require specific controls.
The assessment should identify appropriate measures for reducing these risks.
Other Relevant Health and Safety Legislation
The original article referred to several additional regulations:
- Health and Safety at Work etc. Act 1974 – General duties relating to workplace health and safety.
- Personal Protective Equipment at Work Regulations – Requirements relating to suitable workplace PPE.
- Provision and Use of Work Equipment Regulations 1998 (PUWER) – Requirements for suitable equipment and its safe use.
- Electricity at Work Regulations 1989 – Duties relating to electrical systems and work activities.
Employers should consult current legislation and applicable guidance when developing their electrical safety arrangements.

HSE Enforcement and Arc Flash Risk
The original article highlighted enforcement activity involving electrical arc hazards.
It reported 37 HSE enforcement notices relating to arc flash during an unspecified historical period.
These notices were described as including both improvement and prohibition notices.
Why Electrical Safety Enforcement Matters
Enforcement action may identify weaknesses in electrical risk assessment, equipment safety or workplace procedures.
However, the circumstances of each case determine which legal requirements apply.
For this reason, organisations should not rely on historical enforcement figures alone when assessing their responsibilities.
Instead, they should ensure that electrical hazards are identified and managed through suitable working arrangements.
Network Rail’s Response to the Godinton Substation Incident
An incident at Network Rail’s Godinton Substation in December 2018 prompted further discussion about arc flash protection.
The original article reported changes to PPE arrangements for particular Network Rail Distribution and Plant maintenance and project personnel.
These arrangements applied to specified activities within traction and non-traction distribution locations.

Arc Flash PPE Requirements Described in the Article
The original article identified the following clothing arrangements:
- Main clothing layer: Arc flash polo shirt and arc flash cargo trousers.
- Base layers: Natural 100% cotton or approved flame-retardant garments.
These requirements reflect the arrangements reported at the time. They should not be treated as Network Rail’s current PPE policy.
Workers must follow the latest applicable Network Rail standards, employer procedures and site-specific risk assessments.
Are All Railway Contractors Adequately Protected?
Integrum Power Engineering questioned whether enhanced protection should extend to a wider range of civil engineering and utility contractors.
For example, workers excavating near live electrical cables may face serious hazards even when their primary task is not electrical maintenance.
Therefore, the assessment of arc flash exposure should consider the actual work and electrical environment.


Underground Cable Strike – Amey Contractor Case Study
The original article described a serious underground cable strike involving a contractor working on behalf of Amey in May 2015.
The worker was removing the bottom of a concrete service box using a handheld breaker to install a cable duct.
During the work, the tool struck a live 11kV electrical cable beneath the structure.
Consequences of the Cable Strike
According to the original account, the worker suffered an electric shock and severe burns after their clothing caught fire.
The injuries affected several areas of the body and required extensive medical treatment.
The article reported that the worker spent two weeks in a medically induced coma and underwent multiple skin grafts.
It also described lasting injuries affecting eyesight, heart rhythm and hand function.
These details demonstrate the potentially devastating consequences of contact with underground high voltage cables.
Safety Improvements Following the Incident
The article reported that Amey reviewed its procedures following the accident.
Actions described included:
- Reviewing safe systems of work.
- Reassessing electrical risk management.
- Introducing enhanced arc flash PPE requirements.
- Appointing an Electrical Duty Holder.
- Improving risk assessment procedures.
- Providing additional supervisor training.
These actions were reported in the historical case study. Current company procedures may differ.
Preventing Underground Cable Strikes
Before excavation, contractors must plan the work and identify underground services.
For example, cable records, locating equipment and suitable digging methods can help reduce the risk of accidental contact.
Powered excavation tools can present particular dangers when used close to live electrical cables.
Therefore, workers must follow the approved excavation methodology and relevant safety guidance.
Never assume a buried electrical cable is safe to strike or disturb.
Arc Flash Risk Management – Six Good Practices
Integrum Power Engineering identified six practical measures for improving arc flash safety.
These measures can help organisations develop a structured approach to electrical risk management.
1. Assess Arc Flash Incident Energy
Where appropriate, calculate the potential incident energy and arc flash boundary for relevant electrical equipment.
These calculations help engineers understand the thermal exposure associated with particular fault conditions.
2. Provide Suitable Equipment Information
Identify where equipment labels or other safety information are required.
For example, labels may communicate calculated incident energy or relevant PPE requirements where specified by the organisation’s safety arrangements.
3. Reduce Incident Energy Where Practicable
Assess whether engineering or operational measures can reduce the potential severity of an arc flash.
For example, equipment design and protective device operation may influence the duration and consequences of a fault.
4. Carry Out Task-Based Risk Assessments
Assess the hazards associated with the specific work being undertaken.
This is particularly important when workers may be exposed to electrical equipment or live underground services.
5. Provide Suitable Training and Competence
Workers need to understand relevant electrical hazards and the precautions required for their tasks.
Training should support safe working procedures, incident prevention and correct PPE use.
6. Include Contractors and Visitors
Electrical risk management must consider everyone who may be affected by the work.
For example, contractors and visitors should receive the safety information relevant to their access and activities.
These six measures can support a wider programme of electrical safety management.
Is an Arc Flash Study a Legal Requirement in the UK?
UK legislation requires suitable and sufficient assessments of workplace risks, including relevant electrical hazards.
However, it does not prescribe a single universal arc flash calculation or study for every electrical installation.
The necessary assessment depends on the equipment, working conditions and potential exposure.
What Must Employers Consider?
Employers must identify electrical hazards and implement reasonably practicable precautions.
For example, the risk assessment may need to consider:
- The electrical system and available fault energy.
- The tasks being undertaken.
- Potential exposure to energised equipment.
- The likelihood and consequences of an electrical fault.
- Safe isolation and working procedures.
- Engineering and operational controls.
- Required worker training.
- Appropriate PPE for remaining risks.
Specialist calculations may be necessary to support the assessment in some circumstances.
However, competent technical judgement is required to determine the appropriate method.
Arc Flash Awareness – Research and Industry Attitudes
The original article referred to research associated with ProGARM and the British Safety Industry Federation (BSIF).
The survey highlighted concerns about employer and employee understanding of arc flash responsibilities.
Historical Survey Findings
The article reported the following results:
| Reported Result | Survey Finding |
|---|---|
| 84% | Reported understanding the risks associated with arc flash. |
| 57% | Reported awareness of someone who had suffered an arc flash injury. |
| 90% | Supported revised government guidance or additional legislation addressing arc flash hazards. |
| 25% | The article reported that this proportion of employers placed sole responsibility for arc flash protection on employees. |
These figures reflect the research quoted in the original article. The full survey methodology and sample details were not provided in the supplied text.
Employer and Employee Responsibilities
Electrical safety requires cooperation between employers and employees.
However, employers cannot transfer their statutory duties to workers simply by supplying PPE or issuing instructions.
Suitable risk assessments, safe systems of work and appropriate training remain essential.
Workers also have responsibilities to follow relevant procedures and use protective equipment correctly.
Should Arc Flash PPE Be Required for More Railway Contractors?
The original Integrum article challenged the industry to consider stronger protective arrangements for civil engineering and utility contractors.
Its central concern was that workers outside traditional electrical maintenance roles could still face serious arc flash hazards.
For example, excavation near buried power cables can expose workers to electrical risks even when their work is primarily civil engineering.
Therefore, PPE requirements should be determined by the assessed hazards rather than job title alone.
Arc Flash PPE Is the Last Line of Defence
Protective clothing can reduce the consequences of some arc flash exposures.
However, it cannot prevent an excavation tool from striking an electrical cable.
Consequently, organisations must prioritise appropriate risk controls before relying on protective clothing.
The goal is to prevent the incident wherever reasonably practicable and protect workers against any remaining risks.
ProGARM Arc Flash Clothing and Protection
Thorne & Derrick supply ProGARM arc flash protective clothing for suitable electrical and industrial applications.
The range includes coveralls, trousers, polo shirts, jackets, gloves and other protective garments.
However, the correct PPE must be selected according to the applicable risk assessment and product ratings.

Polo Shirts | Jackets | Coveralls | Trousers | Gloves | Sweatshirts | Helmets
Arc Flash Clothing for Rail and Utility Contractors
Suitable protective clothing may be required during a range of electrical and infrastructure activities.
For example, these can include:
- Electrical substation work.
- Switchgear maintenance.
- Underground cable installation.
- Utility excavation.
- Electrical testing and commissioning.
- Power distribution maintenance.
- Railway electrical infrastructure work.
The required protection depends on the risks identified for the task.
Featured ProGARM Arc Flash Clothing
The original article featured the following 10 ProGARM garments.
We’ve retained their product references, photographs and links. Current ratings and availability should be confirmed before ordering.
|
|
|
|
|
|
|
|
|
|
Download Your Guide to Arc Flash Protection
Understanding arc flash hazards is an important part of managing electrical safety.
Our guide provides further information about electrical arc hazards and protective clothing.
Further Reading – Arc Flash Safety
Explore our related articles covering arc flash hazards, electrical safety and protective clothing.
- Arc Flash Clothing for Highways, Street Lighting and Utility Contractors.
- Arc Flash Dexterity Gloves from ProGARM.
- ProGARM Arc Flash Coveralls.
- Arc Flash Legislation and Regulations.
- Arc Flash PPE – Seven Top Considerations.
Thorne & Derrick – Arc Flash Clothing and Electrical Equipment
Thorne & Derrick International supply specialist equipment for LV, MV and HV electrical installation and maintenance.
Our range includes arc flash clothing and protection for suitable electrical work activities.
We also supply cable accessories and electrical safety equipment for utility, rail and industrial infrastructure.
Related Electrical Equipment
- Electrical Safety Equipment.
- MV and HV Cable Joints and Terminations.
- Cable Duct Seals.
- Cable Cleats and Supports.
- Cable Glands.
- Cable Jointing Tools.
- Cable Pulling Equipment.
- Earthing and Lightning Protection.
Enquire About Arc Flash PPE
Need protective clothing for railway, utility or electrical contractors?
Contact Thorne & Derrick to discuss product specifications and availability.
Please provide the protection requirements identified by your electrical risk assessment so our team can help identify appropriate garments.
VIEW ARC FLASH CLOTHING AND PROTECTION