Blog

HV Cables | Underground Cable Tunnel Pull 400kV By ABB

July 6th, 2021
HV Cables | Underground Cable Tunnel Pull 400kV By ABB

HV Cables | Underground Cable Tunnel Pull 400kV By ABB

Cable Pulling & Laying

ABB manufactured, installed and commissioned the 400kV cable for the National Grid’s largest ever tunnelling project, called ‘The London Connection’, a 20km long 400kV underground cable to supply central London which was energised in 2005 and which was at the time one of the longest 400kV underground cables in Europe.

The need

With electricity demand in North West London and the City increasing twice as fast as the national average and projections showing that this growth would be sustained for a decade, National Grid set out a project called The London Connection designed to create a three phase high voltage supply for North West London and the City.

Essential to National Grid’s future licence to operate, the connection linked Elstree to St John’s Wood through a new three metre diameter, 20km long tunnel to a new £60 million substation, also constructed by ABB.

Project details

ABB manufactured a total of 61km of high-voltage cable using cross-linked polyethylene (XLPE) insulation technology, which eliminates the need to use old-fashioned oil and high maintenance gas filled cables. A similar ABB 400 kV XPLE underground cable has been in service in Berlin since 1998.

The cable was manufactured at our own plant in Germany and underwent a one-year duration test at an independent test facility, where it was signed off as fit for purpose.

Three phase HV AC cable installed in the tunnel

Three phase HV AC cable installed in the tunnel

ABB supplied 150mm diameter cable for three 20km lengths – one for each of the three phases of the supply. At a total weight of 2,440 tonnes, the act of pulling the cable along the length of the tunnel was an element of the project that threw up significant challenges.

ABB delivered the cable to site on 63 massive separate cable drums and pulled it through the tunnel in three sections at intermediate shafts along the length of the tunnel, with the longest cable pull being around 7.5 km. ABB used a special arrangement of cable pulling equipment for the safe and smooth installation through the tunnel. A post-pulling cable insulation test proved that the cable was ready for safe service as part of the grid.

As a full turnkey project, ABB’s successful installation of the cable and connection to the new St John’s Wood substation meant that the London Connection was ready for National Grid to operate in summer 2005 and it has been in operation providing energy to London consumers ever since.


Cable Pulling & Laying Equipment

Suppliers & Distributors

Thorne & Derrick distribute the most extensive range of Low & High Voltage Cable Installation & Electrical Distribution Equipment to the Power Transmission & Distribution industry in the onshore and offshore wind, solar, rail, oil/gas, data centre, battery storage and utility sectors – this includes the most extensive range of Cable Pulling & Cable Laying Equipment to enable the installation of low, medium and high voltage power cables into underground trench or duct.

We service UK and international clients working on underground cables, overhead lines, substations and electrical construction at LV, 11kV/33kV and up to EHV transmission and distribution voltages.

Key Products: MV-HV Cable Joints & Terminations, Cable Cleats, Duct Seals, Cable Transits, Underground Cable Protection, Copper Earth Tapes, Cable Jointing Tools, Feeder Pillars, Cable Ducting, Earthing & Lightning Protection, Electrical Safety, Cable Glands, Arc Flash Protection & Fusegear.

Distributors for: 3M Electrical, ABB, Alroc, Band-It, Cembre, Centriforce, CMP, Elastimold, Ellis Patents, Emtelle, Furse, Lucy Zodion, Nexans Euromold, Pfisterer, Polypipe, ProGARM, Prysmian, and Roxtec.

  • Scope –single-source supply of extensive range of products
  • Stock – a multi-million pound stock holding provides complete global supply solutions
  • Staff – technical support from a trained, proactive and friendly team
  • Delivery – UK stock turnaround with express logistics to all international destinations
Cable Pulling & Laying Equipment

Thorne & Derrick International, based in the UK, are delighted to announce they have entered into an Approved Stockist Agreement with SEB International, the market-leading Cable Laying Equipment manufacturer.

How Important Are Wearer Trials When Buying Arc Flash PPE?

July 6th, 2021

How Important Are Wearer Trials When Buying Arc Flash PPE?

Arc Flash PPE from ProGARM

In a heavily regulated world where garments have to be tested to incredibly high standards, people specifying arc flash clothing and PPE would be forgiven for relying only on the test results when making their decision.

But those results are just one part of a large jigsaw of information you need when making a purchasing decision. How your team feels about wearing the kit should also be part of the puzzle. But how important are wearer trials for Arc Flash PPE?

ProGARM Arc Flash Hoodie

ProGARM Arc Flash Hoodie


MEETING MINIMUM ARC FLASH PPE STANDARDS

To do its job properly – and potentially save a life – Arc Flash PPE has to meet the standards set out in IEC 61482, the international standard for Arc Flash and flash fire hazard protection.

All our garments will have been tested using either open arc or box tests, and will have been given a Cal Rating, which can be cross-referenced with the Arc Flash Study and risk assessment for the task it’s needed for.

But tests don’t tell the full story.

Of course you need to ensure your PPE meets the criteria you need it to, but if you’re looking at kit from three different suppliers which can all meet the standards you’re looking for, how will you make a final decision? Wearer trials are a great way to inform that choice. ProGARM Arc Flash Garments & Clothing Protection

WHAT IS A WEARER TRIAL?

A wearer trial gives people in the field the chance to try out the PPE and garments that you’re considering purchasing while actually doing the job. It means they can experience what it’s like to wear the jackets, trousers, polo shirts and other garments while performing the tasks they are expected to.

When trialling garments ask for feedback about comfort, fit, whether the wearer can move, bend and stretch the way they need to for the tasks they do. Ask whether there are enough pockets, and are they in the right places? All of these factors are important as the kit needs to not only protect from hazards but enable the wearer to get on and do their job.

Arc Flash Helmets & Visors | Selection Guide | Helmets & Visors for Protection Against Arc Hazards

Arc Flash Helmets & Visors | Helmets & Visors for Protection Against Arc Hazards

WHY ARE WEARER TRIALS IMPORTANT &
HOW DO THEY MAKE YOUR TEAM SAFER?

PPE needs to enable people to do their job, while giving them protection from hazards. But it is only as good as their willingness to wear it properly.

For any Arc Flash protection garment to do its job effectively it must be worn properly buttoned or zipped up so that parts of the skin aren’t exposed to a potential Arc Flash blast, which could lead to a whole host of injuries. That’s why we take great care in the cut and fit of all our garments and include what might seem like small details to make our garments very comfortable. One example would be on our jackets where we have added a soft comfort strip at the top of every zip so it doesn’t rub the chin or neck.

Another would be knowing that a lot of the tasks our wearers have to undertake involve kneeling down, so we’ve created pockets for knee pads in our trousers and coveralls.

And while the majority of our end users are men, we also have a women’s range which isn’t just a shrunk down version of the men’s garments. We’ve carefully created new patterns so that our kit for women fits properly.

So, while your new Arc Flash PPE has to meet the criteria set out in your risk assessments, this isn’t the only information you should rely on when choosing new kit – wearer trials are a crucial piece of the puzzle too.

If you want to speak to one of our sector experts about our Arc Flash and fire-resistant PPE, including how important user acceptance testing for Arc Flash PPE is, give us a call.



💡 Did you know? – While high voltage equipment does increase the likelihood and intensity of arc flash explosions, they can occur in any live electrical environment – even low voltage.

Further Reading


Arc Flash Learning & Resources

Arc Flash

Thorne and Derrick are proud to be distributors of ProGARM arc flash coveralls and protection.

We can help – should you require arc flash calculators or advice on the type of clothing and protection available please do not hesitate to contact us.

Arc Flash Trousers Category 2 10 Cal Hi Vis Orange Arc Flash Trousers Category 2 9 Cal Arc Flash Trousers Category 2 9.5 Cal Arc Flash Lineman Coverall Category 2 9.5 Cal
ProGARM 4690 Coverall ProGARM 4616 Trouser ProGARM 5816 Trouser ProGARM 7638 Trouser ProGARM 6458 Coverall
Arc Flash Trousers Category 2 9.5 Cal Hi Vis Yellow Arc Flash Coveralls Category 2 9.5 Cal Hi Vis Yellow Arc Flash Polo Shirt Category 1 Hi Vis Orange Arc Flash Coveralls Category 2 12 Cal Arc Flash Polo Shirt Category 1 Hi Vis Yellow
ProGARM 7418 Trouser ProGARM 7480 Coverall ProGARM 5290 Polo Shirt ProGARM 6444 Coverall ProGARM 5286 Polo Shirt

T&D Logo

The Trackside Conduit

July 6th, 2021

The Trackside Conduit

  • Special thanks to Paul Darlington from the Rail Engineer magazine for kind permission to republish this article

Data connectivity is vital for all aspects of society and industry, and is becoming increasingly important for railway operations. Signalling, electrification control, fixed and radio communications: all rely on cables running alongside the railway.

However, the integrity and value of these rail cables is only as good as the protection offered by the lineside cable route. Often overlooked or taken for granted, it is vital for the safe, efficient operation of any railway.

The primary function of any form of cable route is to protect the cables within.

Ideally it should provide mechanical protection, so it must be robust and stable, fire and vandal proof, capable of being opened and closed to maintain the cables or run new ones, be cost effective and safe to install, and require minimal maintenance.

Cable routes can be constructed from a variety of materials and come in different sizes and shapes. Transition modules may be required along with ‘T’ junctions, bends and joint bays.

All these requirements are not easy to achieve and can conflict. An assortment of route types have been used over the years and the search for an ideal cable route is never ending.


An evolutionary approach

The first types of cable routes were open copper wires raised on wooden poles. With the introduction of overhead electrification, signalling and telecoms cables were run at ground level in some form of cable containment. On the majority of non-electrified lines or those with conductor rails, cables are now provided at ground or sub-surface level.

Wooden cable routes were used initially, but these soon rotted and have not been used for many years. Asbestos cable routes mounted on posts were then provided, but these didn’t offer much mechanical protection and introduced a health and safety risk.

One of the more successful systems was concrete ground-level troughing, generally known as GLT. With detachable lids, this has been used for many years and is supplied in various sizes, generally in 1m lengths.

It provides reasonable mechanical strength, although the natural walkway it forms encourages its use as a lineside pathway. It was not designed for this purpose and a misaligned lid can easily cause injury if walked on.

The weight of concrete troughing gives it reasonable stability, but makes it difficult to handle manually and its installation can require extensive possessions for off-loading.

Deeper and higher ballast shoulders have, in places, transformed the troughing into ballast retaining walls or totally burying it. Any displaced alignment may put strain on the cables within and make it even more hazardous to walk on. While concrete troughing is reasonably inexpensive for the protection achieved, it is costly to install with manual labour and requires frequent replacement of damaged lids

In the 1960s, to obviate many of the disadvantages of the precast concrete route whilst retaining its inherent advantages, a continuous slip-formed concrete route was trialled. A train with an earth plough formed a trench alongside the track. Concrete was then discharged from the train into the trench, after which the train made a further pass with a plough to create a trough in the concrete. Once dry, precast concrete lids were off-loaded.

This method removed much of the manual labour involved in construction, but required a site with soil suitable for the earth plough, precise control of the concrete mix consistency, accurate rate of discharge into the trench and consistent train speed. It was also found that an unplanned thunderstorm turned a near-finished length of route into a disaster area! The trial was abandoned.


Buried cables

In areas of theft risk, cables can be buried directly in the ground at a depth providing adequate protection. Installation is generally required immediately after the trench has been dug as heavy rain can collapse it prior to backfilling. Alternatively, a duct system can be buried prior to the cables being pulled through or, in the case of fibre cables, blown through with compressed air.

Any buried route is expensive to install – particularly with manual labour – and may require rail-mounted machinery for excavation. Gaining access to the cables requires careful selection of the breakout point locations, together with jointing bays. The chosen cable must be suitable for direct burial and it is not easy to subsequently connect into the cable route.

Another method of direct burial is by utilising a rail or vehicle-mounted mole plough.

This is a hydraulically controlled plough blade, with the cables fed through trackside conduits in the blade.

In the right situation the method has some advantages, but large cables can present problems as certain types of soil do not consolidate and can leave a damaged embankment or cess. The method requires careful planning and preparation, with robust buried service checks prior to the cable-laying.

It only takes one old signal base to break the plough and seriously delay the programme. In locations with sharp stones, additional cable protection is required with sheathing or sand backfill. However, ploughing small fibre cable ducts could be an answer for the future. We’ll come back to that later.


Plastic routesPlastic Cable Routes

Over the years, various sorts of plastic cable routes have been trialled for lineside cable containment. Unfortunately, they have generally not provided the required mechanical strength, especially when faced with ballast alongside the route. Plastic also contracts and expands as the temperature varies and it is not easy to incorporate adequate expansion mechanisms.

Railtrack had some success installing a 100mm plastic surface pipe with thermal expansion mitigation which was staked into the ground every few metres. This provided protection to a telecoms cable running between signal boxes on rural routes and is still in use 25 years later. This wasn’t suitable for larger volumes of cables on main lines and it wasn’t easy to provide regular cable breakout points.


Recycled polymer

Over the last ten years, cable routes made from 100% recycled polymers – such as polypropylene – have been introduced which offer similar high strength and impact resistance to traditional concrete, but are approximately five times lighter for the same size and far easier to cut.

A further enhancement – building on the problem of walking on narrow concrete lids – was the introduction of a combined cable route and safe walkway, also made from recycled polymer. Two routes with the equivalent capacity of two concrete troughs were located under a 700mm wide non-slip surface. The lids were constructed so that cables could be laid with half the route open. Fixings were also provided for a removable handrail and the ability to secure the lids to the troughing to deter cable theft.

Following removal of the lids for installation purposes, there have been reports of a route’s sidewalls being deflected inwards due to the weight of the adjacent ballast, preventing the lids being replaced correctly.

This caused the lids’ outer edges to be unsupported and move unexpectedly under the weight of footfall, thus creating a trip hazard. This illustrates the need for maintenance of all cable routes and, in this case, to ensure the lids were securely attached to the sidewalls and not displaced from their correct positions.


Elevated troughingElevated Cable Troughing

In cuttings susceptible to slippage, the toe cannot be excavated to accommodate a trough or buried route, so an elevated troughing route may be required, mounted on posts which only interfere with the soil formation at a minimal number of points. As well as early use of asbestos, elevated troughing has been constructed from a variety of materials over the years including timber, cement, glass-reinforced plastic, metal, recycled polymer and glass-fibre reinforced concrete (GRC).

Many elevated routes lose their alignment during their lifetime due to movement in the soil foundation and are particularly prone to damage as they form an obstruction to track work and make natural seats. Nevertheless, elevated GRC routes have, in particular, been widely used and are easy to transport and install.


Theft & vandalism

Vandalism and theft of copper cables have produced particular problems. Concrete routes may require lids to be fixed with metal clips or epoxy adhesive to deter theft.

In high-risk areas, cables have been sealed into GLT with concrete, but this is generally not recommended as cement can harm some cable sheath types and filling the trough route with concrete makes it unusable for other cables.

It is also expensive and labour intensive. Putting blobs of concrete in the trough is not good either as thieves have been known to cut and steal the intervening length, making it difficult to run a replacement cable.

Buried routes are quite effective as a deterrent if sufficient depth is maintained and the soil is well consolidated, although it has proved necessary in some locations to anchor the cables to prevent them being pulled from the ground using road vehicles.


Fibre cables – Trackside Conduit

When the national fixed telecoms network was deployed by Network Rail, a heavily armoured variant of the normal armoured optical fibre was chosen to deploy without any cable route. This was known as Double-Insulated Super Armoured Cable or DI-SAC which was approved for use where only optical fibre cables were required.

DI-SAC comprised 24 single-mode optical fibres divided equally into two stainless steel tubes, helically wound around a solid aluminium former, encased inside a medium-density polyethylene inner sheath and thick steel-wire armour, with a green over-sheath of fire-retardant ethylene vinyl acetate.

In walking areas and those prone to vandalism, DI-SAC was scratch-buried so it did not protrude above ground level. Nominally, it was secured into the ground every 40m, but this distance varied to prevent the DI-SAC being pulled onto the track. Its use without a cable route was questioned by many in the industry, but it saved the national fibre project several hundred million pounds. The cable was specially made in high volumes and is no longer commercially available.


Blown fibreFibre Optic Technology

Fibre optic technology has now become the norm for telecoms transmission as it provides huge data transmission capability, solves the problem of inductive interference with long distance copper cables and has no theft value.

Fibre cables were traditionally installed in concrete trough routes in lengths of up to 2km. Selected fibres would be broken out to connect to the digital transmission equipment. Originally, such equipment would use local copper cable tails to provide connections to equipment such as telephones, data terminals, radio base stations and signalling interlockings.

With the introduction of all-IP (internet protocol) networks, fibre-borne digital signals right to the end device are now becoming the norm which has led to the concept of ‘blown fibre’ as an option.

This involves a composite material pipe incorporating several ducts of different sizes being installed either on the surface or buried. Bundles of fibres can then be blown into the duct using compressed air and further bundles can be similarly installed into different tubes at a later date, as required.

One drawback of normal routes is that new cables tend to be laid on top of existing cables in the route. When new signalling or telecom systems are brought into use, the redundant cabling remains in place and the trough becomes over-full. With fibre blowing it is relatively easy to remove fibre bundles and replace them should this be required.

Conventional troughing routes and copper cables are far larger than the blown-fibre solution and more expensive to install. As the blown-fibre duct can be coiled and directly ploughed into the ground using smaller machinery, it may be more cost effective and flexible than traditional buried routes.

Blown fibre has been trialled in Scotland for lineside installation, but is yet to receive national approval due to concerns with route expansion. At the very least, blown fibre may be a good option for fibre in buildings and stations.

So, the search for the ideal cable route and trackside conduit continues in order to maintain the integrity and value of the vital cables which support a safe, efficient railway.

Original Source Rail Engineer Magazine article written by Paul Darlington 


About Rail Engineer

Rail Engineer

Rail Engineer is the leading independent quality monthly magazine for engineers, project managers, directors and leading rail executive decision makers.

Besides publishing the latest up-to-date rail engineering news, our team of engineer writers report on the engineering and technical aspects of many of the major projects being undertaken day in, day out, above and below ground, and across the globe.

In the UK we work in close consultation with Network Rail, Docklands Light Railway and the Underground, where our team of rail engineers actively visit the project sites, meet project engineers and provide in-depth analysis on the engineering skills being used and the latest innovations.

From trams and fleet refurbishment to new rolling stock and high speed rail, the rail engineer reports on the engineering and environmental challenges for manufacturers and operators. Our engineers visit factories and depots, meeting with specialist engineers to bring you the latest engineering updates on all aspects of rolling stock, whether onboard technology or mechanical enhancements focussing on safety, energy and the passenger experience.

RAIL ENGINEER MAY / JUNE 2021

Click here to view the latest edition below or click the following link where the original The Trackside Conduit Article can be found https://www.railengineer.co.uk/rail-engineer-may-june-2021-hs2s-largest-bridge-decarbonising-scotland-and-piccadilly-line-trains/


Paul Darlington joined British Rail as a Trainee Telecoms Technician in September 1975. He became an instructor in telecommunications and moved to the telecoms project office in Birmingham, where he was involved in designing customer information systems and radio schemes. By the time of privatisation, he was a Project Engineer with BR Telecommunications Ltd, responsible for the implementation of telecommunication schemes included Merseyrail IECC resignalling.

With the inception of Railtrack, Paul moved to Manchester as the Telecoms Engineer for the North West. He was, for a time, the Engineering Manager responsible for coordinating all the multi-functional engineering disciplines in the North West Zone.

His next role was Head of Telecommunications for Network Rail in London, where the foundations for Network Rail Telecoms and the IP network now known as FTNx were put in place. He then moved back to Manchester as the Signalling Route Asset Manager for LNW North and led the control period 5 signalling renewals planning. He also continued as chair of the safety review panel for the national GSM-R programme.

After a 37-year career in the rail industry, Paul retired in October 2012 and, as well as writing for Rail Engineer, is the Managing Editor of IRSE News.


Thorne & Derrick are leading Specialist Distributors & Stockists of LV, MV & HV Cable Installation, Jointing, Substation & Electrical Equipment to the Rail industry.

Thorne & Derrick

Thorne & Derrick are leading Specialist Distributors & Stockists of LV, MV & HV Cable Installation, Jointing, Substation & Electrical Equipment to the Rail industry.


Network Rail

RAIL CABLE ACCESSORIES, ELECTRIFICATION
& INSTALLATION EQUIPMENT

Thorne & Derrick stock and distribute an extensive range of 400V-33kV Rail Cable Accessories & Power Distribution Systems including feeder pillars to contractors undertaking Low Voltage Power Distribution, HV Electrification & Substations, DC Traction & Networks, OLE and Track Feeder Cable Renewals – complete range of Network Rail PADS approved track terminations, cable joints, cable repair and connection products up to 25kV, including 3M Cold Shrink, Pfisterer CONNEX and Nexans Euromold products.

3M Nexans Pfisterer

Cable Joints, Terminations & Connections | Distributors & Stockists for 3M Cold Shrink | Nexans Euromold | Pfisterer CONNEX


GRP Cable Trough | GRC Cable Trough | Concrete Cable Trough | Cable Ducting

A Model For Cable Containment

July 6th, 2021

A Model For Cable Containment

Cable Support & Containment

  • Special thanks to Paul Darlington from Rail Engineer for kind permission to republish this article
    

MITA Powered by WIBE is a major multi-national company, operating in a wide range of sectors including Rail, Utility, Data-centre, Renewable, Oil & Gas and Process industries – the company’s extensive Cable Support range includes a market-leading range of GRP Elevated Cable Troughing & Accessories which are designed and manufactured in the UK.

GRP elevated cable troughing is an especially useful containment system for rail.

Ground Level Troughing (GLT) is used in signalling and telecoms schemes for the cable connections to lineside equipment such as points, train detection, signals and radio sites.

However, in many places, GLT cannot be used due to the ground profile and steep embankments and cuttings. GRP is an ideal alternative for such locations and it is also essential for large current-carrying power cables, such as medium voltage 25kV trackside power cables.


MITA WIBE is the leading “fit & forget” Cable Troughing & Management System manufactured in GRP with PADS Approval and specific material formula’s for trackside and tunnel applications on Network Rail infrastructure.

MITA WIBE is the leading “fit & forget” Cable Troughing & Management System manufactured in GRP with PADS Approval and specific material formula’s for trackside and tunnel applications on Network Rail infrastructure.

Mita GRP

MITA are marker-leaders in the manufacture of GRP non-metallic troughing, GRP cable ladders, CABSYS cable trays, ducts, cable support channels and Fibastrut as the brand continues to lead the industry towards a sustainable future for a wide range of low (LV), medium (MV) and high voltage (HV) cable installation applications.


High quality manufacture

The MITA GRP is produced by pultrusion technology.

This uses a combination of unidirectional and cross-strand glass mat which is resin-impregnated and pulled through a hot die to produce a very solid, structurally sound profile with excellent mechanical rigidity.

Unlike some other troughing systems, MITA GRP does not contract or expand with heat causing the troughing route to distort. It is produced with a high quality of manufacture and modified by the use of additives to the resin, and with protection from ultra-violet light. The product is produced in either 3m or 6m lengths for easy transportation and installation.

MITA GRP is 70% lighter than steel and 90 times lighter than concrete; the cable trough is also corrosion resistant. It does not conduct heat and has excellent durability against adverse weather conditions. The rail cable management product offers excellent UV stability resulting in a cost-effective long-term solution.

The MITA GRP is provided in a wide range of trays, troughing and ladders which can support any type of cable – especially power and fibre cables which require a gentle bending radius. Unlike some competitors’ systems, MITA TM elevated troughing is provided with GRP support posts to increase its durability.

The troughing lids clip securely in place, providing cable theft protection. Further security can easily be added by installing stainless steel bands around the elevated route.

MitaTM GRP troughing in use on the East Coast Main Line

MitaTM GRP troughing in use on the East Coast Main Line


Network Rail approval

The MITA GRP elevated cable route has been fully approved by Network Rail under Certificate of Acceptance PA05/00442 issued in 2015 for use in locations unsuited to GLT. The Zero Halogen Low Smoke (ZHLS) version has also been approved for use in sub-surface stations and connecting tunnels.

Furthermore, the approval applies to a very impressive 42-page list of accessories, including bends, brackets, risers and transition/reducer pieces. Allowing connections to existing GLT cable routes, reducers are important and not always available in other cable containment systems.

London Underground has successfully used MITA GRP troughing. They were concerned that their sensitive signalling equipment was susceptible to contact by flakes of galvanisation from steel support systems and that their DC traction cabling system might create eddy currents within troughing ladders and supports if they were metallic.

MITA GRP troughing was chosen as it is non-magnetic and has non-conductive properties. The ZHLS version is also a requirement for London Underground’s sub-surface locations.

The cable containment system is not just used in rail, but has also been successfully employed in a wide range of industries including data centres, power industries, manufacturing, water treatment, food production, industrial buildings and oil and gas.


Working with GRP

Another particularly useful feature of the MITA GRP system is its ability to be integrated with the Bentley Raceway and Cable Management Building Information Modelling (BIM) tool.

This provides a complete layout, routing and material estimating function in a single, integrated system. It can be applied from the initial concept design through to detailed design and construction.

A user can create an accurate 3D model of the cable troughing route, making it easy to ensure that adequate space and clearances are available in confined locations, and for the detailed design and material requirements to be quickly and easily produced.

MITA GRP is a non-hazardous, inert product – the cable support system is lightweight and can be manually handled without difficulty, unlike concrete. In contrast to steel, GRP does not have to be deburred or given edge treatment before fitting, saving time and further reducing labour costs. During installation, any cutting, drilling, bonding and jointing can be easily undertaken and will not give rise to a hazardous situation, with any dust kept to a minimum.

Sample Components of the MITA GRP Troughing System

Sample Components of the MITA GRP Troughing System


Andrew Sillars, Contractor Specification Engineer, says: “Having supported the specification of Glass Reinforced Polymer cable containment since 2005, I have experienced its unique features such as light weight, long-life durability, no deburring, no earth bonding and many more. All these advantages of GRP Cable Containment support a cheaper, quicker and easier-to-install system that gives a true fit-and-forget solution.”


About Rail Engineer

Rail Engineer

Rail Engineer is the leading independent quality monthly magazine for engineers, project managers, directors and leading rail executive decision makers.

Besides publishing the latest up-to-date rail engineering news, our team of engineer writers report on the engineering and technical aspects of many of the major projects being undertaken day in, day out, above and below ground, and across the globe.

In the UK we work in close consultation with Network Rail, Docklands Light Railway and the Underground, where our team of rail engineers actively visit the project sites, meet project engineers and provide in-depth analysis on the engineering skills being used and the latest innovations.

From trams and fleet refurbishment to new rolling stock and high speed rail, the rail engineer reports on the engineering and environmental challenges for manufacturers and operators. Our engineers visit factories and depots, meeting with specialist engineers to bring you the latest engineering updates on all aspects of rolling stock, whether onboard technology or mechanical enhancements focussing on safety, energy and the passenger experience.


RAIL ENGINEER MAY / JUNE 2021

View the latest edition below or click the following link where the original The Trackside Conduit Article can be found https://www.railengineer.co.uk/rail-engineer-may-june-2021-hs2s-largest-bridge-decarbonising-scotland-and-piccadilly-line-trains/


Paul Darlington joined British Rail as a Trainee Telecoms Technician in September 1975. He became an instructor in telecommunications and moved to the telecoms project office in Birmingham, where he was involved in designing customer information systems and radio schemes. By the time of privatisation, he was a project engineer with BR Telecommunications Ltd, responsible for the implementation of telecommunication schemes included Merseyrail IECC resignalling.

With the inception of Railtrack, Paul moved to Manchester as the Telecoms Engineer for the North West. He was, for a time, the Engineering Manager responsible for coordinating all the multi-functional engineering disciplines in the North West Zone.

His next role was Head of Telecommunications for Network Rail in London, where the foundations for Network Rail Telecoms and the IP network now known as FTNx were put in place. He then moved back to Manchester as the Signalling Route Asset Manager for LNW North and led the control period 5 signalling renewals planning. He also continued as Chair of the Safety Review Panel for the national GSM-R programme.

After a 37-year career in the rail industry, Paul retired in October 2012 and, as well as writing for Rail Engineer, is the Managing Editor of IRSE News.


Thorne & Derrick are leading Specialist Distributors & Stockists of LV, MV & HV Cable Installation, Jointing, Substation & Electrical Equipment to the Rail industry.

Thorne & Derrick are leading Specialist Distributors & Stockists of LV, MV & HV Cable Installation, Jointing, Substation & Electrical Equipment to the Rail industry.


Thorne & Derrick are leading Specialist Distributors & Stockists of LV, MV & HV Cable Installation, Jointing, Substation & Electrical Equipment to the Rail industry.

RAIL CABLE ACCESSORIES, ELECTRIFICATION
& INSTALLATION EQUIPMENT

Thorne & Derrick stock and distribute an extensive range of 400V-33kV Rail Cable Accessories & Power Distribution Systems including feeder pillars to contractors undertaking Low Voltage Power Distribution, HV Electrification & Substations, DC Traction & Networks, OLE and Track Feeder Cable Renewals – complete range of Network Rail PADS approved track terminations, cable joints, cable repair and connection products up to 25kV, including 3M Cold Shrink, Pfisterer CONNEX and Nexans Euromold products.

3M Nexans Pfisterer

Cable Joints, Terminations & Connections | Distributors & Stockists for 3M Cold Shrink | Nexans Euromold | Pfisterer CONNEX

ELLIS Solus Single Cable Clamps For Non Metallic Market

July 6th, 2021

Solus Single Cable Clamps

Non Metallic Single Cable Clamps

Ellis Solus Single Cable Clamps for Cleating Cables

Ellis Patents have boosted the strength of their cable clamps and cleats range with the launch of Solus single cable clamps. This range of non-metallic single cable clamps are suitable for cables from Ø25 to Ø75mm. Designed, developed and manufactured in-house by Ellis, Solus cable clamps are made from a high strength, glass-filled nylon and joins Trident – a trefoil clamp – as part of their expanding non-metallic product range.

Single Cable Clamps

Features

  • Short circuit & mechanically tested in accordance with IEC61914
  • Cleats manufactured from high grade heat stabilised polymer
  • Suitable for indoor, outdoor and harsh environments
  • Long design life
  • Easily stacked cable clamps for multiple cables and circuits
  • Large cable range (fewer clamps sized to stock)

ELLIS Solus Single Cable Clamps For Non Metallic Market

Danny Macfarlane, Managing Director of Ellis Patents, said: “Non-metallic cable cleats have been very popular in mainland Europe for many years, and their use is now growing swiftly in the UK and many of the export markets we operate in around the world.”

“Their benefits are numerous but key is the fact that they have extremely long lifespans meaning the cleats can be used practically anywhere, including in extremely harsh environments.”

The reason for Solus’ extremely long lifespan is that the glass filled nylon material used is a high-grade engineering polymer. The new range of cable clamps is also fully stackable, meaning additions to cable runs can be made without having to disturb any cables already installed. Solus also features different mounting options that enhance its installation versatility; and because the product can accommodate a wide cable range, customers can stock small numbers of units to cover a wide range of cable sizes.

“Innovation is very much at the heart of everything we do, and Solus is the latest in a long line of new and improved cable management products to have come out the Ellis Patents Innovation Hub here in Rillington,” added Danny.

Key to Ellis’ ability to innovate is its ability to take products from initial ideas through to IEC61914:2015 compliant products; with its in-house Innovation Hub incorporating 3D printers, FEA analysis and a fully equipped testing laboratory.Ellis Patents | Stockists & Distributors

Solus Single Cable Clamps

Specification

Ellis Solus Single Cable Clamps - Dimensions

Ellis Solus Single Cable Clamps – Dimensions

 

Ellis Solus Part Number SL25-38GFN SL36-52GFN SL49-75GFN
Cable Range Min ∅ (mm) 25 36 49
Cable Range Max ∅ (mm) 38 52 75
Liner Size (mm) 3 3 3
Cable Range with Liner Min ∅ (mm) 19 30 43
Cable Range with Liner Max ∅ (mm) 32 46 69
Dimensions W (mm) 100 116 138
Dimensions H (mm) 80 95 124
Dimensions D (mm) 60 77 77
Dimensions A (mm) 24 24 26
Dimensions P (mm) 60 75 95
Dimensions ∅ M12 M12 M12
Weight (g) 290 370 493
ELLIS Solus Cable Clamps

ELLIS Solus Cable Clamps

Further Reading


THORNE & DERRICK

Thorne & Derrick are national distributors of LV, MV & HV Cable Installation, Jointing, Substation & Electrical Equipment – servicing businesses involved in cabling, jointing, substation, earthing, overhead line and electrical construction at LV, 11kV, 33kV, 66kV and EHV. Supplying a complete range of power cable accessories to support the installation and maintenance of low/medium and high voltage power systems:

  • Slip-on Cable Terminations
  • Cold-shrink Cable Terminations
  • Heat-shrink Cable Terminations
  • Cable Joints – Heat & Cold-shrink
  • Separable Connectors (Euromold)
  • Surge Arresters & Switchgear/Transformer Bushings

Key Product Categories: Duct Seals | Cable Cleats | Cable Glands | Electrical Safety | Arc Flash Protection | Cable Jointing Tools | Cable Pulling | Earthing | Feeder Pillars | Cable Joints LV | Joints & Terminations MV 

Thorne & Derrick International

Ellis Patents Vulcan, Atlas & Emperor Cable Cleats

Ellis Patents Vulcan, Atlas & Emperor Cable Cleats

Associated manufacturers
Share this page
Share this page
X

Get a quote

Complete the form below to make an enquiry about products.

  • This field is for validation purposes and should be left unchanged.
  • Please enter your full name.
  • Please enter your contact telephone number.
  • Please enter your e-mail address.
  • Please select if you are enquiring about products for the UK or for export.